A completes a work in 12 days whereas B completes the same work in 24 days. If both A and B work together, the work will be completed in ______
6
8
10
12
If 3 persons do 3 times of a particular work in 3 days, then 7 persons can do 7 times of that work in _________.
3 days
5 days
6 days
7 days
Shaista completes a piece of work in 10 days, All completes the same work in 40 days, if they work together, the days required to complete the work will be _________
6 days
8 days
10 days
16 days
12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
6
8
10
12
30 labourer's working 7 hours a day can finish a piece of work in 18 days, if the Labourer's work 6 hours a day, the number of Labourers required to finish the same piece of work in 30 days will be _________.
16
18
20
21
If it was Saturday 17th December, 1982 what would be the day on 22nd December 1984?
Monday
Tuesday
Wednesday
Sunday
Complete the given series. 3, 8, 15, 24, ?
32
34
36
35
What will come next? 7 + 2 -1 = H, 22 + 6 -5 = W, 11 + 6 -2 = ?